Thanks both for the responses. This is currently preliminary. I will be going on site to evaluate the current conditions later in the week. A bit more clarification based on information provided to me which also changes how I want to proceed. It is an exterior prescriptive CMU retaining wall...
I am evaluating an exterior retaining wall that a contractor built to prescriptive codes. They came back after inspection and added two feet of additional retaining height which means insufficient rebar in the wall and inadequate footing sizes. The wall is starting to bow in the middle. The...