How to specify temporary shoring during backfill operation.
Concrete is 70% of specified strengh plus compacting on the heel side.
Are there any recomendations?
Thanks
What a surcharge should be used modeling traffic load next to the cantiliver RW? I use 2.5 ft of soil or 300 psft.
Are there any code recomendations? What about dynamic impact?
Thanks to everybody for responses. I will refer to state DOT standard specification and if,when and where DOT requires prime/tack coat contractor shall apply it.
Russian SNIP used to have uniform load factors (overload) for steel, concrete masonry and wood:
dead load 1.1
snow 1.3
short-term live load 1.3(guess)
long term live load 1.3 (guess)
wind 1.4 plus dynamic component for buildings of certain height
as far as I remember overload factors and...
I think if you use load tables then engineer calcs of the subfloor must confirm that vertical load might be distributed according to joist flexibility(rigities) in lieu of the tributary area.
There are three snow zones in European part of former USSR with ground snow in the range of 50kg/m^2(10psf) -100kg/m^2(20psf), no reduction and drift consideration as in ASCE7.
There are three wind zones in the range of 50kg/m^2(10psf)-100kg/m^2(20psf) at elevation 20m(60ft).