set out the kickers for the core walls, once the kickers are concreted and the formwork is stood use the same co-ordinates you used for setting out the kickers to check the alignment of the top of the formwork and adjust using push-pull props bolted to the formwork and to the slab.
hope this helps.
Good morning all,
Does anyone have a sample or actual risk assessment for LiDAR surveying from aircraft? or know where i might access one.
Thanks
Gary.
hello all,
Pebble mill studios in birmingham was said to be suffering from concrete cancer, i cant find any evidence of this but only people claiming this was used as an excuse by the BBC to demolish the site and relocate. Does anyone know where i might find information on this?