Recent content by JonoJakarta

  1. JonoJakarta

    THD in 20 kV side of 20/0.4 kV Transformer, 3000 kVA, Dyn-5, Year 2019

    Dear bacon4life, THD in current Dear Scottf I think traditional CTs and PTs, There is not mention the manufacture but the data of CT's is :CT, 100-200/5-5A 16kA 30VA cl 0.5 7.5VA 5P15 and for PTs :VT, 15-20kV/V3:100V/V3;cl0.5 30-50VA. About frequency response, i dont have information
  2. JonoJakarta

    THD in 20 kV side of 20/0.4 kV Transformer, 3000 kVA, Dyn-5, Year 2019

    Dear expert, I found in THD our PM5500 meter on our SM6-24 switchboard showing around 50%-52%, I was surprised. Is this coming from load side (LV/0.4 kV) or on HV side? Then, I switch off ACB on LV side of Transformer , it's mean our transformer on no-load condition I checked PM5500 meter on...
  3. JonoJakarta

    Temperature of LV transformer terminal connection is high

    Dear All, I have case in our transformer 20/0.4 kV,2500 kVA, 2002 year, DYn5, Ip, when we did IR thermograph today, 19 July 2022, we found temperature of S phase is 99 deg.C This case is repeateable case before on April 20, 2022. At that time, temperature is 102.5 deg C at same location (S...
  4. JonoJakarta

    Synchronization at 20 kV is Fail

    Dear Bill, this is commissioning new set, 1st time
  5. JonoJakarta

    Synchronization at 20 kV is Fail

    Dear Experts, Last 8 October 2019, we did synchronization between our generator and our grid in 20 kV networking. Our generator is 11 kV and step up by transformer 11/20 kV, 12/15 MVA. The Synchronization is fail. And 87T relay in breaker (this breaker connected between our Transformer and...