  1. jomalopi00

    Resource calendar - how to print it?

    You find the complete procedure under the MS-Project "Help": print a resource notes, calendar etc...
  2. jomalopi00

    Resource calendar - how to print it?

    I went under: View-->Reports-->select the report type you want and click select. If you choose Custom click a report (e.g. Resource) in the reports list, click Edit,and click Details tab. In the Resource box, select the Notes, Objects or Calendars check box (depending your needs). Then click OK...
  3. jomalopi00

    Print preview - legend

    Problem solved, thank you
  4. jomalopi00

    Print preview - legend

    I save every day different version of my project. When I printed the project I had on the footer the legend with my project name and date and the legends about the project. However since today the legend is not anymore displayed. I checked every parameteres in the Setup window and everything...
  5. jomalopi00

    Daily hrs for a resource

    I fixed the work (in hrs)
  6. jomalopi00

    Daily hrs for a resource

    My problem is that I have a resource that at a certain time of the project is underallocated. So I thought I just have to enter on the general tab the Avail from/to fields with the concerned dates with a higher %, but it doesn't work. My duration is not reduced (because % increased) and the work...
  7. jomalopi00

    Resource calendar - how to print it?

    Great I finally found the solution!
  8. jomalopi00

    Daily hrs for a resource

    Thanks a lot for the reply but can you precise how I access the properties page of the resource. Because when I open the resource info window I have the General, Working Time, Costs and Notes tabs. Thank you in advance, because it will help me a lot.
  9. jomalopi00

    Daily hrs for a resource

    If I have 1 resource and many tasks, can I attribute each day different work hours. I.e: 1 week of work and I would like that the resource work 3hrs on Monday, 5hrs on thuesday etc… Is it possible to do this?
  10. jomalopi00

    Resource usage tab

    I have tasks and 1 resource attributed to all tasks. On the Resource usage tab if I change directly the number of hours for a project, the percentage of the resource is not updated automatically on the Gantt Chart. Is it a normal behaviour?
  11. jomalopi00

    Resource calendar - how to print it?

    I have several resources to manage and I added in their calendars holidays and official days off. How can I print the resource calendar to see directly their holidays and abscences? Is it possible to do? Thanks in advance