Yeah, I don't see why you couldn't just mount a ledger to the face of the wall unless your loads are extremely high. And in that case, a little bit of demo to support heavier loads would be anticipated.
It wouldn't? I would anticipate the ceiling/floor joists and the rafters to be lapped and so it's just nails/screws in shear. I don't see a seat cut happening at all in the proposed detail.
In the middle of the wall, or at the top? Middle seems unlikely to be constructable without shoring the wall above until the bond beam can be installed, grouted and cured.
At the top of the wall, I don't see a big problem.
I don't mind this idea. Another alternative would be two DTT2Z connectors, one on each side of the 4x, with a piece of unistrut bolted to them. Would result in a concentric loading, would get the wood fasteners up above the neutral axis, should have substantial capacity and would leave the...
Honestly that's preferable where I am. Because the light gauge is almost exclusively a delegated design item. I want them to say 6" studs, so that we know how much space they've accounted for, and a max spacing in case the cladding is dependent on it. But otherwise I don't want them hard...
Will do, as soon as I figure out how to get architects to stop specifying depth, spacing and thickness of studs in their specs. And then complaining when they get slammed with a large PCN because the specs they used didn't work for the application. 3 5/8" 24 gauge studs @ 24" can't span 16 feet...
I agree with this, removing it all the way shouldn't be difficult. Honestly they may just cut the sill plate at the same time and take the anchor bolts and sill plate out with the concrete. Then you could do a wood or steel header attached to the walls on each side of the opening.
I also must...
In similar circumstances, I've had geotech's tell me to provide a minimum of 12" clear between new and abandoned piles. That's to address the comment @BridgeSmith indicated where the concrete may have flowed outwards from the drilled shaft into a void. From a geotechnical perspective however...
Depending on the soil, a 2:1 embedded to exposed doesn't seem that crazy to me. Then again I'm living in an area with clay as far as you can dig, so our capacities are pretty low.
I would think you'd have to get geotechnical engineer buy in on using the blocks for anything.
Still feels like you're double counting dead loads. 7.5 kN/m^2 is more than the weight of the 220mm thick concrete slab. I'd be inclined to think that the 7.5 should be inclusive of self weight of slab, plus finishes on top, plus M&E hanging allowance. The slab itself weighs around 5.5 kN/m^2...
What torsional movement would you be getting on a footing and stem wall? If this is one of those where the stem wall cantilevers from the footing and they install a partial height wood wall above, then I would call that more overturning moment than torsion, but that's semantics.
A drawing with...