Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by jack36

  1. jack36

    K-Series Steel Joist Shear Strength

    Deadblow, that's a good question. I'll take a shot at an answer... The maximum shear in a beam with a uniform distributed load is at the ends, and it is zero at mid-span, correct? When you cut off 11'-4" of the beam your shear diagram does not stay where it was with only the 11'-4" cut off...
  2. jack36

    K-Series Steel Joist Shear Strength

    Thanks JAE for your input and the link to the document. I have seen that in the past and it has some good information in it. The web bars are solid and are not bent. They extend between the double angle chords and are welded. I believe I'm going to go back and see if I can verify any...
  3. jack36

    K-Series Steel Joist Shear Strength

    I am working on a project where we are designing a modification to shorten some existing K-series steel joists by 11'-4". I plotted my original shear diagram and new shear diagram and found that the shear in the modified joist exceeds the original shear diagram (based on allowable uniform...
  4. jack36

    Hollow-Core Plank - Welding Along Length

    Thanks KootK. Another question for this condition: I have an interior braced frame that is parallel to the plank span. I planned on transferring the diaphragm forces with the embedded plates (4' o.c.). If I eliminate the embedded plates, I'm thinking my only option would be to have the...
  5. jack36

    Hollow-Core Plank - Welding Along Length

    Thanks for the feedback. The beams running parallel with the planks are used to support other beams in the opposite direction. I've got some open spaces to deal with that don't allow for convenient column locations. I specified that shim plates be added as needed to fill the gap due to...
  6. jack36

    Hollow-Core Plank - Welding Along Length

    I have a project with hollow-core planks bearing on structural steel framing. 8" hollow-core with 2" normal weight topping. I have specified the planks must be supplied with embedded plates to allow for welding to the top flange of the steel beams. I'm requiring this where the planks bear on...
  7. jack36

    Cutting Bottom Flange of Steel Beam (In Place)

    I have a project under construction and have a beam that was specified as a W12x50, but they installed a W21x50. The other way around would have been a lot worse, but there are two ducts that need to pass under this beam and a certain ceiling height is required. This is an interior beam that...
  8. jack36

    Occupancy Category for Organ Recovery Building

    I appreciate all the input on this. The architect is not treating this as an essential facility, so I was not going to either. We were thinking that it was not critical because the patients were not alive, but the fact that this building will serve Cat. IV facilities does appear to be a valid...
  9. jack36

    Occupancy Category for Organ Recovery Building

    I'm working on a building where surgery will be performed on deceased individuals to recover organs for donation. There will not be living patients in this building. The donated organs will be transported to other facilities for surgery on the living patient. What are your thoughts on...
  10. jack36

    Stud Wall Connection to Hollow Core Podium

    Thanks Mike for the input. I believe I'm going to upset my exterior beams and lower my interior beams below the slab.
  11. jack36

    Stud Wall Connection to Hollow Core Podium

    I'd like to get some feedback on how other engineers detail the connection of wood stud walls to a hollow-core slab podium level. I initially wanted to upset the steel beam with the top of the hollow-core slab near the top of the beam. That would allow me to shop weld threaded anchors for...
  12. jack36

    Hotel Floor System - Light Gauge Steel Framing

    I'm not familiar with Comslab, but it would be a composite steel deck system. I would be interested in what Ecospan says about vibrations.
  13. jack36

    Hotel Floor System - Light Gauge Steel Framing

    I have a 5-story hotel project coming up. Structural steel will be used up to the 2nd floor due to open 1st floor spaces, but we will go up from there with light gauge steel framing. My previous hotel work consisted of wood framing above the 2nd floor, so I would always use wood trusses for...
  14. jack36

    When to Hire (small structural firm)

    msquared48: I like your very simple strategy. I do feel it is move forward or be left behind. Ron: Thank you for your input. The issue of being happy having employees is something I have thought hard about, and I have heard others express displeasure with having employees. I have thought...
  15. jack36

    When to Hire (small structural firm)

    Thank you berkshire for your helpful input. To clarify, my projected yearly expenses, with the new employee, exceed my previous yearly revenue. I anticipate that I will be able to increase my revenue once I have the ability to take on more projects from some of my current clients and seek new...

Part and Inventory Search