When you have progress on a task and update the baseline for that task you will get some very strange numbers. To rebaseline a task, set the percent complete or physical percent complete to zero then rebaseline the task. Make sure you reflect the correct roll up check box. If you want the...
Under tools / options the calculation tap, there is a box to check if you want the remaining work scheduled from the status date or the actual start date.