  1. ivieje

    Total of Cost Rollups not calculating correctly

    When you have progress on a task and update the baseline for that task you will get some very strange numbers. To rebaseline a task, set the percent complete or physical percent complete to zero then rebaseline the task. Make sure you reflect the correct roll up check box. If you want the...
  2. ivieje

    Setting Planned Finish Date based on Remaining Work

    Under tools / options the calculation tap, there is a box to check if you want the remaining work scheduled from the status date or the actual start date.