Nicam & MBR,
This is a floor slab (the requirement is to seperate the hall with a movable partion system)
There is no other heavy plant machinery load on the floor
The slab thickness is approx 200mm, the span is 6meters-
We just wanted to know if this was feasable, we do intend to use an...
We want to install a top hung movable partition wall/ door system on the top floor of a 4 storey school. We need a beam to hang the partition panels of around 300kg total and to support a stud wall above of approx 250kg. As the storey is partially in the attic with sloping ceilings we cannot...