Thanks FOCHT3 for your info. Those piles near to the cut are physically seen as broken. But when we randomly carry out Pile Integrity Test on those about 10 metres away from the slope, it shows dicontinuity at the first 6 meter. Physically these piles are still seen straight and not swayed. Is...
Would appreciate opinions on this matter. We are currently building a sewage treatment plant and has recently driven 200mm x 200mm x 6000mm length square concrete piles 30 meters below the ground level (pile to length). The contractor has unfortunately excavated the sides of the piles 10ft down...