Recent content by fdolamprea

  1. fdolamprea

    Backing ASME IX

    In the new WPS whith the portion SMAW requires backing (weld metal). That backing is the back weld?
  2. fdolamprea

    Backing ASME IX

    If a PQR states that the GTAW process shall be used on root and fill with SAMW (groove joints) by ASME IX it is performed to make a WPS with only the portion of SMAW which requires backing (back Weld -E7018 ) is allowed to make backweld with backcouging? or it is necessary to make a new pqr?