I tried it multiple different ways, and here are the results:
1) Add Resource 1 @ 75%, and then add Resource 2 @ 75%. Duration calculates at 9.83d. The difference between the Start and End Dates is 13d.
2) Add Resource 1 and Resource 2 @ 100%, then change Resource 1 % to 75%, and then...
I'll try to reword. I have one full-time resource (8hrs/day). That resource can only spend 75% of their time on the task (6hrs/day). I have another resource, which is a part-time resource (4hrs/day). That resource also can only spend 75% of their time on the task (3hrs/day). The 6hrs + 3hrs...
I would like Duration to automatically calculate based on Work and Resources. Project seems to work fine, when using one resource, but using multiple resources, the Duration calculation appears to be off. As an example, I will create a task for 10d (80hrs), and add two resources (one full-time...