    Synchronizing of Photovoltaic power station

    whether the PV system is large or small, they synchronize to Utility at PCC (Point Of Common Coupling)....across 110kV breaker in your case. Since they do not make larger size inverters presently, you will be using about 50 iMVA inverters probably stepped-up to a 35kV level and then across a...