Great, thanks, will speak with Emerson. This is also LNG service. The pictures show exactly what I had in mind. On the extension on the pilot, it looks like two pilots were installed in series.
Hello,
for a ship cargo tank, we have different operational cases with different settings for the safety valves (2 x 100% capacity required to be installed). I am considering to use pilot operated safety valves and install two pilots on each, with different set pressures. The iolation valve to...
Hello,
I am designing piping around 3 parallel centrifugal cooling water pumps.
650m3/hr each, inlet piping 18", outlet 12".
All three pumps have a dedicated inlet pipe, coming from a basin 3 meters upstream. The outlet will be combined into a common header to the plant.
The pump manufacturer...