Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by Dumbo2929

  1. Dumbo2929

    Using Meter Form 35S on 4-wire service

    It is a CT installation with a Class 20 meter. The feed is actually 800A at 480V
  2. Dumbo2929

    Using Meter Form 35S on 4-wire service

    I have a customer with 480Y/277V transformer secondary and has installed Form 35S meter with 2CT's and no PT's. Meter is Elster A3 solid-state. The equipment end use is a PV inverter which is 3-wire, but the transformer is 4-wire, so I feel this should be 9S and not 35S. In addition they...
  3. Dumbo2929

    Using wye PT's on 3-wire system

    We have a 23kV 3-phase 3-wire system to be metered. The only available PT's are single bushing. Would it be accurate to install these in an un-grounded wye connection on the primary side and a grounded wye connection on the secondary side and use a three-phase 4-wire metering set-up? I know...
  4. Dumbo2929

    Overhead Quadraplex Sub Feeder

    I have a service to a building with a conventional 120/028V, three-phase four wire service. There is a sub-panel being installed to a separate structure, and being fed overhead by quadraplex secondaries on poles (3-phase conductors and bare neutral supporting messenger). The question is a...
  5. Dumbo2929

    Auxillary Grounding Electrode Required?

    I know it's commonly done and we specify it on larger projects. This is a small project and I was looking for a requirement in the NEC, because i don't believe there is one.
  6. Dumbo2929

    Auxillary Grounding Electrode Required?

    I have a NEC question. We are installing a new electrical service and panel (outdoors) for a lighting project. The service is single-120/240V and is grounding at the service entrance (outdoor cabinet, panelboard, utility meter) via 2 ground rods. A grounding conductor is run with each branch...
  7. Dumbo2929

    Chain link fencing bonding

    The closest point to from the water tank to the fence is 11 feet.
  8. Dumbo2929

    Chain link fencing bonding

    Can anyone tell me if there is a requirement in the 2008 NEC (because I can't find one) that requires a metal chain link fence to be grounded with an intentional ground rod, etc. under the following situation. There is an existing million+ gallon municipal water storage tank on a site. There...
  9. Dumbo2929

    Arc Flash - Single Layer

    Is anyone well enough versed in NFPA-70E to answer this? Is it required for HRC2 (8 cal/cm2) PPE that 2 layers be worn? Can a single layer of 11 cal such as a coverall be worn, or is some type of cotton undergarment or cotton layer required. My understanding was that HRC 2 needed 2 layers to...
  10. Dumbo2929

    Ground faults tripping main circuit breaker

    I know one on the east coast if that is closer for you www.PowerEngineersLLC.com
  11. Dumbo2929

    Transformer Differential Ground Relay

    Can anyone point me to the calculations need to set a transformer 87G differential ground relay? I have a customer with a nuisance trip and we believe it is set too low. I'm looking for a good explaination of the calculation. It's a delta-wye substation transformer 69kv-13.8kv, 18MVA.
  12. Dumbo2929

    Cathodic Protection water line under 115kV

    Does anyone have any good articles, or links to basics of cathodic protection of ductile iron water pipe running perpendicular under a 115kV transmission overhead right of way??
  13. Dumbo2929

    Induction Generator Parameters

    Can anyone point me to a good link with the formulas or a spreadsheet that would be helpful in calculating transient, subtransient, etc. generator paramenters for induction generators. I have some work for a number of generators in the 100kW range and want to verify some vendor information and...
  14. Dumbo2929

    Overhead distribution fusing

    Does anyone have a good link for a paper, article, reference giving a simple discussion of utility overhead distribution protection, particularly related to transformer and line fusing on overhead systems. I'm looking for a good reference for the technically challenged.

Part and Inventory Search