We are getting ready to file a NOT with the NYSDEC. We were performing stormwater inspections up until now; my question is do we still need to continue performing these inspections now that the NOT is filed or does the NOT signify the complete end of inspector's needs as well?
Thanks
The repair is taking place in NJ. Essentially the liner of the basin (45000 sqft) needs to be replaced, and it's been projected as a 2 month project. Odds are, I'm going to have an issue with a storm event coming through
A client needs to fix the liner in their stormwater basin, because they never performed regular maintenance on it. What would anyone suggest for addressing the issue of having to deactivate the basin from stormflow during construction? Would creating a temporary dam and pumping the runoff...