Yes, I figured it out. There is an option within the customize fields, under Graphical Indicators. I few boxes above that you can check: Nonsummary, Summary or Project Summary.
I'm doing various columns and calculations. But for this particular example one of the column is a customized for completeness. It takes the % complete values and breaks them into 0-33% (white circle), 34-66% (half circle), 67-100% (full circle).
But still same problem. The overall...
Can someone tell me how to get graphical indicators to work at a rolled-up level? I get can them to show up only at a task level but not at a sub-project or project level (rolled up tasks).
Look at this link. The yellow cells show the location where I would like indicators to show up...