Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by ChipperB

  1. ChipperB

    Effect of mixing exist base material and high PI subgrade and Lime Stabilizing

    I am rebuilding an old road in Texas. The proposed section is 1.5" type'D' Hmac over 2.0" Type 'B' HMAC over 8.0" A2Base, over 6" lime stabilized subgrade. The existing road section was thicker than the proposed because of 9-inches of existing asphalt. What would be the effect of mixing...
  2. ChipperB

    Using Base Course for Road Surface

    Thanks Ron. I too had thought about cement stabilizing. Also, Texas we have something called black base, which is just asphalt impregnated base. The TxDOT A1 base is supposed to be good unconfined when its compacted, but the A2 base-not so much.
  3. ChipperB

    Using Base Course for Road Surface

    I am reviewing a set of plans that constructs a new road over an existing road. The existing road is on a 5 percent grade and shows a lot of erosion and some bare rock outcropping. When it was first built it caused a lot of flooding to the area downstream at the bottom of the hill. The 22-foot...
  4. ChipperB

    Concrete Time for Curing

    We have a two week window to get the project done. We are building a 6-in. thick, 6-ft. X 6-ft. reinf concrete slab on 6-in, compacted crushed stone, to support a small condensor unit. Using 3000 psi concrete. After slab is poured, how many days before we can safely install the unit? Any...
  5. ChipperB

    Traffic Signal Installation Cost Estimating

    Thanks bridge buster, never would of thought of that.
  6. ChipperB

    Traffic Signal Installation Cost Estimating

    Hey guys and gals, I am assembling a Design-Build contract to signalize an existing intersection. I need to do a cost estimate, so I know how much funding to request. Does anyone know where I can get prices on mast arms, traffic and pedestrian signal heads, traffic signal control cabinets...
  7. ChipperB

    12-foot Tall Chain Link Fence with Privacy Slats

    I need to install a 12 -foot tall chain link fence that has privacy slats in it. Location is San Antonio, Tx. Soil is Houston black clay. What type of wind load is recommended to design for? How deep would conc. piers for the fence posts need to be?
  8. ChipperB

    Flexible Pavement Subgrade Question

    ishvaaag-We have a standard 1 year warranty. In my experience, even mediocre paving will hold up pretty well- for the first year. After that is when deterioration really begins. We have a chance to avoid future liabilities now, but what we pay extra now will be far less than we would have to...
  9. ChipperB

    Flexible Pavement Subgrade Question

    We have high clay soils in this area of Central Texas and this is a high volume of traffic street (arterial). The contract was awarded with the contractor having Option A- 2.5" HMAC over 8" crushed limestone compacted base course over 6" lime stabilized subgrade or Option B 2.5" HMAC over 12"...
  10. ChipperB

    Underground Detention System Concerns

    I am reviewing at set of plans that use an underground detention system to control post development flow. An open field will become a large parking lot. I have concerns because the soils are clay with a high PI. This system is actually more of a retention system because the outlet pipe is 2.5...
  11. ChipperB

    How do I Size ditch for Parking Area Flow

    All, thanks for your help. To jgailla, the the total acreage that drains to the site is 2.7 ac. 1.7ac parking area and 1.0 ac. undeveloped, but rocky, not much vegetation, and sloped. I designed for the 25 year storm. I developed a composite "c" of 0.97. My Q=cIA is...
  12. ChipperB

    How do I Size ditch for Parking Area Flow

    gbam, slope of the ditch is 2.33%.
  13. ChipperB

    How do I Size ditch for Parking Area Flow

    gbam, forgot to tell you if I combine the offsite and onsite drainage areas and use the longest Tc the flow rate is lower than the onsite flow rate.
  14. ChipperB

    How do I Size ditch for Parking Area Flow

    I determined the velocity using the following equation: v = (20.3282)*(S^1/2) for paved surface S= 0.074 ft/ft thanks
  15. ChipperB

    How do I Size ditch for Parking Area Flow

    I am working with a large (1.7 ac) asphalt parking area that drains to an existing ditch located parallel to the parking area's down stream edge (see attached sketch). This ditch also receives flow from 1.0 ac of undeveloped land. I think the existing ditch is undersized because it appears to...

Part and Inventory Search