Thank you for your response.
Here's what I am trying to do.
I am doing a cycle time analysis on patient visits for a medical office. They have say 20 patients coming in say from 9-12 in the morning. The clinic is collecting time data on each patient from the time the enter the door to leaving...
I am a MS Project newbie. I am trying to perform a cycle time analysis using Project, and I am just looking for Gantt charts. Each activity lasts a few minutes only. I want to enter the start and end TIME for each activity and want MS Project to calculate the duration. eg. Step 1 starts at 9:00...