    relation between work and duration?

    Yes, the predecessors column. By studying the program I found a way to do as I think to: Resource leveling hour by hour, looking for overallocations. This seemes to work.
  2. chepe35

    relation between work and duration?

    thanks, folks, but...I just have inserted the "work" column, and I have put the planned work hours in there. And I marked the pre-defined persons (are able to work no more than 8 hrs daily) in the "resources" column. Now what I expected was that the work to be done by the...
  3. chepe35

    relation between work and duration?

    Hello friends, as a newbie I try to plan as I ever did (on paper): Define resources (persons), estimate work hours of each sub-task and then - expect to see the duration of the task. But the program only shows me under "Duration" the longest work time of all the related sub-tasks, but...