I don't have much more information unfortunately. This is from a WFLHD Bridge Project Special Contract Requirement which seems to obviate the FP-03 subsection (SCR vague and confusing, plans no help). The job has grout pads for EM p/c girder bearings, grout key joints between precast girders...