On a recent project our Middle East Client requested corrosion coupons be placed at the 6 o'clock position as opposed to the 12 o'clock position on the pipe. There are several problems this has created.
1) Pipe is large diameter 36", 30", 16" and 4" but all pipe is buried 1 meter to TOP and a...