Thank you, darth. I have only tested a few dozen slabs but there has yet to be a time when everyone didn't beg for it to be done ASAP. I do respect the fact that some projects have things scheduled for certain reasons. But if given the option, I have much better things I'd rather do in the...
Thank you for the replies, everyone. I guess my question is, regardless of who is supposed to do what and when, will saw cutting affect the FF/FL numbers? Would there be any difference testing as soon as the slab is ready, and before they saw cut as opposed to the following morning after saw...
I apologize if this has been covered but I was unable to find anything after doing a quick search.
A problem I have faced several times with contractors onsite is that we are often "bullied" and eventually cater our schedule to test FF/FL prior to saw cutting operations, even though the...