I have to install a chilling unit for cooling down a natural gas flowrate which can vary between 1,25 MSCM/day and 2,5 MSCM/day.
The choice can be: two complete chilling units with a 1,25 MSCM/day design; but, in order to save capex, could I use a single condenser, a single evaporator, and two...