Thanks for the help guys, I agree with moving the 25kV circuit to the top. I was trying to save some time as this is only supposed to be a temporary feed.
Hi all,
I am wondering if someone out there can help me out with a question about phase spacing. Currently our system has two 12kV circuits on a pole line. The top is energized and the bottom is spare.
The need for a 25kV line has arouse and I was wondering if I could use the spare bottom...