I've seen durations change because I changed the Units % (found under Resource tab when bring up Task Information). While sometimes I purposely do this to reflect reality (i.e., person working 2 projects), perhaps a data entry mistake was made with the wrong tab being displayed?
In new project, using Gantt view, create a new task- call it "Clean Out Garage". Double-click to bring up task information, and under [Advanced] tab, ensure task is of type "Fixed Units" and "Effort driven" is enabled. Assign 2 resources to task: Husband at 100%...
I've found Project's documentation lacking. While there's a lot of documenation available, it seems to be "how to" information, not "this is what this term means" or "why". For example, I tried to find a definition of the term "fixed units" The...