Sorry I haven't visited the forum in a while.
Just to let you know, the pile cap was poured with a mix design which included 25% flyash, but no addition of any ice (despite my concerns) to control the initial concrete temp. which went in at about 90 degrees. Day time temps were runing about...
We have made them aware of ACI's recomendations including the 3 ft criteria, but they don't seem to care. They'll start early in the morning and they do have some fly ash in the mix which should help but they are not going to add any ice or chilled water in the mix.
Thanks for your comments:
1 They plan to cast full height in one pour, which has me worried as well since they do not intend to take any precautions such as chilled water, ice or insulating blankets (nothing really).
2 I am not sure about the magnitude of the up lift since I was not envolved...
As part of the on site QC team, I am concerned about thermal cracking in some up-coming pile cap pours which are over 10 ft thick, 15 ft wide and 20 ft long. However the designers have declared that these are not really mass concrete pours and no speacial precations need to be taken.
1. If...
As part of the QC team on site I am concerned about thermal cracking on some up-coming pile cap pours which are over 10 ft thick, 15 ft wide & 20 ft long. However the designers advise that these are not really mass concrete pours and no speacial precautions need be taken.
1 If none of the...
As part of the QC team on site I am concerned about heat of hydration and thermal cracking on several up-coming pile cap pours which are over 10 ft thick, 15 ft wide & 20 ft long. However the designers have advised us that they are not really to be considered as mass concrete pours and we need...
I agree with Jike and others above: be careful about bonding agents. If you chip out only the loose or fractured concrete (even if it leaves the holes rough and irregual) the repairs may be small enough to consider an epoxy grout rather than a bonding agent with cementitious material. I think...
All butt fusion machines that I know of require a grip on the pipe itself so any exterior insulation (CMP) would have to be stripped back. However such a machine may exist, so I suggest you search the net & talk to the equipment manufacturers.
Butt welding machines are generally larger &...
CRSI Manual of Std. Practice does not actually recommend #3 standees. For slabs 2 ft thick & less you should use #4 standees (see section 3.14.2) spaced at about 3-4 ft.
Further to the ACI & ASTM references above you can go to faceco.com/40q.htlm (40 most asked questions about F numbers). This was put together by Face Company who make profile surveys and/or equipment to do so. I have not used them or their equipment, but they seem to know a lot about it.
I do...
Sorry I missed your post, I don't often look under Concrete Formwork.
I spent a number of years working in the United Arab Emirates and a lot of Turkish rebar was used there, some good, some bad. I don't recall the KWT mark, but it has been a few years since I worked there. I suggest you...
Anchoring into rock is rather speacialized work and you might want to contact "Williams" or another manufacturer that makes rock anchors. Regardless of what the numbers say I would also do a pull test on a couple of installed anchors just to be sure the rock, grout & anchor are all working...