Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by 1952mike

  1. 1952mike

    Rubber pad mount bolt torque value

    Thanks for your reply. That is right, we have added load distributing large area steel pads to distribute bolt head concen. load to a larger area, and some other changes. My only intention for posting this was to obtain info on bolt torque so not to exceed rubber compressive load limit. Mike
  2. 1952mike

    Rubber pad mount bolt torque value

    Yes, I also imagined torque value will be low, that is why I thought to post my question to make sure I am not making a mistake. Currently the box is mounted rigidly on the foundation and is cracking at the bolted area due to high vib. If we use rubber pads, we will have to use lock nuts &...
  3. 1952mike

    Rubber pad mount bolt torque value

    The pad is sandwiched between a foundation and the rigid box and is "completely" supported (sandwiched) by the foundation and the box (so the bolt load will be distributed almost equally). Rubber is 40 Durometer. If more than 50 PSi is applied it just compresses and its isolation eff. is...
  4. 1952mike

    Rubber pad mount bolt torque value

    I seem to be having a fine time calculating bolts tightening torque value for the following situation: A 1000 lbs rectangular box sits on two rubber pads of 1" thick and 4" wide x 18" long at the ends of box. There are (4) 1/2" bolts (2 each end) that need to be tightened, but the max allowed...
  5. 1952mike

    Skid supported at multiple points

    I went through Roark "formulas for stress & strain" 5th edition and could not find any solution for a beam supported on 14 points. All of examples & formulae are for simply supported beams. I have one equation and 14 unkowns. Any reference to a specific edition or page number?
  6. 1952mike

    Skid supported at multiple points

    Hi there! Would some one give me a hint on how to tackle this issue? Have a skid of about 40' long that is supported on 14 (7 each side) vibration isolators. The supported unit weighs about 130,000 lbs. Isolators have equal space through out the skid length. CG is at 15' from the left. Here...
  7. 1952mike

    Pressure loss - miter cut pipe or tube

    Many thanks katmar! [thumbsup2] Mike
  8. 1952mike

    Pressure loss - miter cut pipe or tube

    Thanks "BigInch"! Any hint on how to get "equivalent length"? I have forgotten most of these that I knew once.[morning] Mike
  9. 1952mike

    Pressure loss - miter cut pipe or tube

    Thanks katmar for replying. You are correct. This is for exhaust gas at around 650 °F. Reason I didn't say it was because i was interested in methodoloy, not accuracy at this time. So, I guess i need to get exh gas density involved in 33 feet to get its pressure loss in PSI? Am I right...
  10. 1952mike

    Pressure loss - miter cut pipe or tube

    Hi there! I am at loss, need helpful hints. I need to calculate pressure loss thru a 30" ID formed tubing miter cut and welded together to form a 45° & a 90° elbows. 90° has two miter cuts. 30" leg length. Looking at Crane data book I see that for alpha=45° =15fT, and for alpha=90° K=60fT. OK...
  11. 1952mike

    Chiller & electric cooling ton-hour

    If I understand your comment correctly, the offset would be in the order of 4,800,000 * 0.6 = 2,880,000 ton-hour (or even half that amount 2,400,000) am I right? Thanks Mike
  12. 1952mike

    Chiller & electric cooling ton-hour

    The system is not a turbine, but couple of gas engines driving generators, and using exhaust gas & the jacket water heat to heat up absorbtion chiller's hot water circuit. The customer has this requirement that by running the system for 8000 hours a year & powering 600 ton chiller, we need to...
  13. 1952mike

    Chiller & electric cooling ton-hour

    Hi all, If I have this Co-Gen unit that can generate enough hot water to power a 600 ton absorbtion chiller and the system runs about 8000 hours a year, then what would equivalent "ton-hours" of electric cooling be? I am guessing it would be 600 * 8000 = 4,800,000 ton-hour of electric cooling...
  14. 1952mike

    Gas engine backfire

    Actually, If you return to http://www.eng-tips.com/viewthread.cfm?qid=130088&page=1 and see my posting (third posting after yours), you will notice that I replied to my question basically using your method here. Thanks anyway.

Part and Inventory Search