Planning plant maintenance shuts
Planning plant maintenance shuts
(OP)
Hi
I'm trying to get all the work we do during a single days maintenance shut into a gantt charted plan. At present we just issue lists of hundreds of jobs with no priority or duration estimates. I've tried MS Project but it seem to be biased towards projects with tasks measured in days or weeks. Is there a way I can configure it to plan a project over a single day so that e.g. start TIMES are displayed for each task instead of start DATES
Cheers
I'm trying to get all the work we do during a single days maintenance shut into a gantt charted plan. At present we just issue lists of hundreds of jobs with no priority or duration estimates. I've tried MS Project but it seem to be biased towards projects with tasks measured in days or weeks. Is there a way I can configure it to plan a project over a single day so that e.g. start TIMES are displayed for each task instead of start DATES
Cheers





RE: Planning plant maintenance shuts
When entering duration hours, enter the number followed by the letter "h".
I'm not sure about how to add/configure columns to display Start and Finish clock hours.
Bernard Ertl
InterPlan Systems
- eTaskMaker Project Planning Software
- ATC Professional Turnaround Management Software
RE: Planning plant maintenance shuts
Cheers
P