INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Calculation Alarm/Trip Levels in 3-phase Flooded-Weir Separator

Calculation Alarm/Trip Levels in 3-phase Flooded-Weir Separator

Calculation Alarm/Trip Levels in 3-phase Flooded-Weir Separator

(OP)
Dear All,

I've developed a software which calculates the alarm/trip levels (heights in meters) for the 3-phase Separators. They'r calculated on the base of the liquids' hold-up timings. (if the height of a particular level is less than some specific minimum value (meters), then it sets to this value). As the shape of the separator is not very simple the direct calculation is impossible as you could see, so I've used some iterative method to come-up with the height of each level.

The samples of those levels:

Not sure how useful this program can be as I did it for the particular project of the separator upgrade and appreciate any suggestions on !!!

thanks,
Joisy

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.