I am trying to do the following steps
1. Open MS Project
2. Create a task
3. Make the duration as 1 day
4. Go to the right plane
5. Drag the task to make it for 2 days
6. Now the task duration column shows 1.88 rather than 2 days.Why?
Please help.
1. Open MS Project
2. Create a task
3. Make the duration as 1 day
4. Go to the right plane
5. Drag the task to make it for 2 days
6. Now the task duration column shows 1.88 rather than 2 days.Why?
Please help.





RE: MS Schedule
When smallest timescale is set to days, the smallest change I can get is 0.5 days