INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Pile rebar projection, hooked or not?

Pile rebar projection, hooked or not?

Pile rebar projection, hooked or not?

(OP)
On the c.i.p. concrete pile std dwg, we usually provide two details of dowels to the contractors. 1. straight, the dowel is the extention of the pile vertical rebars. 2. hooked (90 degrees or 180 degrees) with other end embeded into the pile concrete.  My question is, in construction practice, which one is better (or popular)?

In my understanding, straight dowel in the first case is required when the pile embedment depth is a variable because overlap may be inevitable. But the problem thus is the pile-cap shall be much deeper to accomodate the straight projection.

Thanks in advance for comments

RE: Pile rebar projection, hooked or not?

The preferred method would be "1. straight".  This method takes advantage of continuity at the pile to cap connection, which is important for seismic consideration (where plastic hinges may occur).

Your 2nd detail allows the contractor an easy "fix" if the pile is embedded beyond the expected elevation, which is OK if formation of a hinge is not a consideration.

If formation of a hinge is a consideration, you might consider detailing a lap splice near the mid-height of the column, with a long enough lap to allow for variance in the embedment depth (i.e. if your min. splice length is 54" then detail a lap splice of 54"+24" to allow for the column to extend 2' further than anticipated)

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources