Global stability
Global stability
(OP)
When should a global stability review be carried out when design a bridge foundation .
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
|
RE: Global stability
RE: Global stability
stability was not carried out by the designer or his geo firm. I believe it was there belief that the reinforced earth wall supplier they single sourced would carried this out.
It is know my understanding that on integral abutments the embankments are part of the structure therefore if the global stability was not carried out we have a big problem on our hands,the worst slope will be 1 to 1.3.
RE: Global stability
A '1 to 1.3' slope is pretty damn steep - how tall will it be? How long? Soil and groundwater conditions?
Please see FAQ731-376 for great suggestions on how to make the best use of Eng-Tips Fora. See FAQ158-922 for recommendations regarding the question, "How Do You Evaluate Fill Settlement Beneath Structures?"
RE: Global stability
I practice in the U.S. in Ohio. The way that the transportation department does MSE contracting is the have prequalified MSE designers perform the design function. The geotechnical engineer will make some reasonable assumptions up front in terms of dimensions of the wall and run settlement and stability analyses. Once the design is complete, there should be a check on the original assumptions. The MSE designer is responsible for the internal stability of the wall only.
When there is a stub abutment bearing in the MSE wall, there must be a greater degree of coordination between the MSE designer and the geotechnical engineer. Also, for this case a higher factor of safety is generally required.
Good luck
RE: Global stability
I agree with the statements of the two above. I've been involved with MSE wall design for nearly 10 years in both the public and private sectors. Based on what I have observed it is rare to find a wall designer who will take responsibility for external (global) stability. I interpret the reason for this is that if global stability is adequate, the MSE wall designer doesn't spend anymore money having to "understand" the subsurface conditions. However, having said that, I am also aware of many MSE wall vendors who are capible of completing a turnkey package (total design from global to internal stability), but I typically see this relationship on the private side of the practice.
If this isn't convoluted enough, realize that proper scoping of services up front would have made things much clearer (i.e., if the vendor is to complete all design, that should have been stated under the original contract so the original engineering firm would not be carrying budget for it). Unfortunately, many geotechnical proposals are very vague in describing their scope of services and statements such as "provide recommendations relative to the geotechnical design of the retaining walls" are worse than saying nothing at all. Your problem isn't entirely an engineering problem, it's a project problem.
It's sticky, good luck!
Z
Zdinak
RE: Global stability
RE: Global stability
RE: Global stability
A design/build contract would have been more appropriate had the DOT wanted the contractor to assume design functions as well -
Please see FAQ731-376 for great suggestions on how to make the best use of Eng-Tips Fora. See FAQ158-922 for recommendations regarding the question, "How Do You Evaluate Fill Settlement Beneath Structures?"
RE: Global stability
BigH is correct at when global stability should be completed. However, I have come across projects where global stability is left to the contractor. This creats a problem if the contractor does not understand what they are to do before they bid. In the furture at any time you encounter projects where portions of the engineering are not completed or required by others (say a MSE firms), the contractor should contact a geo before biding to ensure all costs associated with project are in place. I had to deal with this problem after contractor bid, and they were not happy (not with me) after they realized that changes regarding base preparation had to be made. And yes no one checked global stability until it fall on my lap, after bid prices were sent in.
regards
RE: Global stability
RE: Global stability