INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Expander Recompressor System

Expander Recompressor System

Expander Recompressor System

(OP)
Our ethylene plant uses a three stage expander on the H2 and methane demethanizer product vapor to recover the refrigeration power for the demethanizer reflux and feed chilling. The liquid methane and hydrogen/methane vapor from the expander outlet are the only refrigeration available for the plant below the -150F level. Recompressors on the other side of the expander shafts bring the hydrogen up to 120psig. It is the recompressor discharge pressure which is controlled, the expander outlet pressure is the result from the power balance. Currently our expander speeds are lower and discharge pressure higher than design, with the result that nowhere near design methane liquid is being generated and the refrigeration being produced is low. This is leading to excess ethylene losses. It is believed the expanders worked at design shortly after being installed, but these problems appeared after a subsequent plant restart.

My question is:
Since the expander discharge pressure is not controlled, can there be more than one stable operating point and/or feasible start-up path issue for this type system?

My thought is that the additional methane that must be compressed is creating added power requirement for recompression that will not exist when the process actually gets to design isentropic efficiency on the expanders. I want to bleed some gas to fuel (or flare) before the recompressors to get the expander speed up to design, but there is no piping to do this. Tie-ins do exist and I think the idea has a good chance of success, but I have met some resistance because the system seemed to be working at one time. Any input is appreciated.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources