INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Projecting Finish Dates

Projecting Finish Dates

Projecting Finish Dates

(OP)
How do you show project finish dates that are based on the actual start and % completion?  For example, I have schedule where I entered actual start of 11/12/03, duration is 10 working days and task is 80% complete.  Project is showing a finish date of 11/25/03.  How can this be true if today is 3/4/04 and the task is not yet complete?

RE: Projecting Finish Dates

You can't get Project to do that, as there's no good way for Project to estimate your run rate under all conditions.  

What you can do is to baseline the schedule and put in the new estimated end date.

TTFN

RE: Projecting Finish Dates

How about splitting the task and moving the unfinished part to todays date?

DC

RE: Projecting Finish Dates

You could "progress" your project and get all unfinished work to complete after a date specified by you.

RE: Projecting Finish Dates

It has been along time since I have used project but I think that once you update each task you need to update the project.  Goto tools-tracking-update project.

RE: Projecting Finish Dates

Complementing what WillRussell said, that is the best way to forecast your end date. The way to do it is:

- Enter the advance per activity.
- Make sure you tell MSProject the status date of the project by going to Menu>Project>Project Information>Status Date (here you enter the status date)
- Then go to Tools>Tracking>Update Project
- Check the radio button "Reschedule uncompleted work to start" (put the status date if other)
- Press OK.

Project will reschedule uncompleted work (your remaining 20%), i.e. 2 days in your example, to start from the status date on.

Note: if after doing this, it is not showing an accurate en date as it will happen, then you have to modify the duration of your activity.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources