INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

hydrotesting of cross country pipeline

hydrotesting of cross country pipeline

hydrotesting of cross country pipeline

(OP)
Can anyone please tell me the formula for calculating the  following:-
We have a 10.5 Km 12" Size LPG Cross Country pipeline .Material of Construction is API5LGRB. The Pipelineis  7.9 mm thick. I would like to carry out Hydrotest the above  pipeline to a pressure of 25.0Kg/Sq.cm. Kindly advise the time taken and the probable capacity ofthe hydrotest pump. Alternatively , kindly tell me the time taken with a pump of capacity 10 Litres /min .Prior to pressurising , I have already filled the entire pipeline, full of water to a pressure of 14.0 Kg/Sq.Cm using some other centrifugal  pumps. From here i will have to raise the pressure to 25.0 Kg/Sq.cm. Kindly advise the formula.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.