export data from Ms. Project to excel adds "h" or "d" string
export data from Ms. Project to excel adds "h" or "d" string
(OP)
When I export data from Ms. Project to excel, project adds to duration and work the “h” or “d” string. How can I solve this without use Edit/Replace in Excel?





RE: export data from Ms. Project to excel adds "h" or "d" string
TTFN
RE: export data from Ms. Project to excel adds "h" or "d" string
That´s the reason beacouse i want to remove those strings.
RE: export data from Ms. Project to excel adds "h" or "d" string
Since the "h" and "d" are a factor of 8 different, you would need to convert everything into hours or days or whatever, which is something you would have to do in Excel anyway. Only after you convert to a single time unit will it make sense to do what you're talking about.
TTFN
RE: export data from Ms. Project to excel adds "h" or "d" string