rehabilitation of ogie type dam
rehabilitation of ogie type dam
(OP)
the existing overflow type dam for an irrigation project spans 30m across the waterway with a height of 6m.
built without an apron slab on the downstream side, the dam is undermined and is hanging supported only by the abutments on both banks.
any suggestions on how to rehabilitate.
will filling up the gap under the existing dam be sufficient.any suggestions?
built without an apron slab on the downstream side, the dam is undermined and is hanging supported only by the abutments on both banks.
any suggestions on how to rehabilitate.
will filling up the gap under the existing dam be sufficient.any suggestions?





RE: rehabilitation of ogie type dam
Filling the gap may well solve the symptom - the gap is a symptom of a problem – and you will need to also cure the problem. Don't make assumptions - I have investigated at least two dams where stilling basins, which were intended to be there to dissipate energy, had been filled in by a well meaning structural engineer with an affinity for pouring concrete.
Get specialist advice – Brian
RE: rehabilitation of ogie type dam
RE: rehabilitation of ogie type dam
Best of luck with yours Brian
RE: rehabilitation of ogie type dam
In Arizona, dam regulations state that a structure is not regulated as a "dam" if:
1) structure is lower than 6 feet from spillway elevation to lowest point at downstream toe.
2) structure is between 6 - 25 feet high with less than 50 acre-feet of water impounded
3) structure is over 25 feet high, regardless of how much water is impounded
As stated by BRIS, similar requirements exist in most developed countries. The risk from dam failure can be substantial if the structure is located in a urbanized area. If this structure is indeed a dam and in a high risk area, I would hire an engineer experienced in dam safety to evaluate and design any fix.
RE: rehabilitation of ogie type dam
You have a typo in your post. I believe that you meant to say (in 3) above) that all structures more than 25 feet high are regulated - and must be treated - as a dam.
I don't consider a 6 meter (almost 20 feet) high wall of water as simply "messy". If you are downstream and close to the failure, you're dead.
To me, the decisions on repair have everything to do with the value of the dam, the consequences of dam failure, and (to a lesser extent) the owner's willingness to accept risk.
Proceed with caution unless you think the dam might fail. If risk to life is great, act decisively to reduce that risk - lower the pool level ASAP. Attempt to fill in the void. Create an apron to reduce the risk of continued erosion. And grout beneath the dam as soon as the void backfilling is complete. You will probably have to engage in several methods of repair at once -
Please see FAQ731-376 for great suggestions on how to make the best use of Eng-Tips Fora.
RE: rehabilitation of ogie type dam
If you think, a diversion scheme can be implemented, the chances of the dam surviving are very good.
Regards.
RE: rehabilitation of ogie type dam
your'e post is right on the mark, but I want to emphasize that if this is a dam, an engineer experienced with dam safety should be doing the design. My first recommendation would be to contact your local department of water resources, dam safety division and get their opinion. If it is a dam, I'm sure they would be more than willing to inspect the dam and recommend a course of action.
Try www.damsafety.org for more info.
RE: rehabilitation of ogie type dam
Please see FAQ731-376 for great suggestions on how to make the best use of Eng-Tips Fora.
RE: rehabilitation of ogie type dam
the ogee dam is a small water impounding structure at the elevated section of an irrigation system with a service area of about 150 hectares.the structure lthough recently concstructed was not provided with as Focht3 noted an apron slab,the cut-off wall wa also omitted and there is no trench core.the flow over the structure is about 5cms(cubic meters per sec.)there is not really any threat posed by the dam to lives and property as these structures are set up way up in the fluviall section of the waterway and is designed as for overflow.
due to deficiencies in construction, the scouring started at the toe of the dam and has progressed due to the absence of a trench core to carve a hole at the base of the dam.
RE: rehabilitation of ogie type dam
Do you know whether the hydrology, spillway design, founding conditions etc. was adequately considered in the initial design?
It would be embarrassing to repair the damage caused by the omission of a stilling basin only for the dam to exhibit failure due to piping or deterioration of the spillway due to inadequate initial design.
RE: rehabilitation of ogie type dam
Please see FAQ731-376 for great suggestions on how to make the best use of Eng-Tips Fora.
RE: rehabilitation of ogie type dam
RE: rehabilitation of ogie type dam
for now the replacement option would tend to be the line we'll pursue.