Close-out report on Basic Engineering of Oil&gas Flowstations upgrade
Close-out report on Basic Engineering of Oil&gas Flowstations upgrade
(OP)
I have being mandated to prepare a close-out report on Basic Engineering of Three Flowsations' upgrade Project for my discipline - Process Engineering. I want an input on how to go about it and the necessary areas to include as regard the Project.





RE: Close-out report on Basic Engineering of Oil&gas Flowstations upgrade
You should include lessons learnt, on time, on budget, contractor performance, your performance, results of commissioning etc. Surley your superiors and/or colleagues can assist.
As part of the project close out you should AS BUILD all drawings and datasheets etc.
RE: Close-out report on Basic Engineering of Oil&gas Flowstations upgrade
don't forget the basics,
the O&M manuals, guarantee
details, manufacturer's contact
details, recommended list
of spares, etc. etc.