INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

cast in place pile reinforcing

cast in place pile reinforcing

cast in place pile reinforcing

(OP)
Is it ok to break cages and do you always use all reinforcing thru-out the entire pile our could you send the reinforcing down a certain depth and the remainder to have no reinforcing.

RE: cast in place pile reinforcing

If you have uplift load or horisontal load on pile you need to have reinforcement as requred for concrete section to support such loads. You may stop this reinforcement at depth where reinforcement is not required plus development length. (Ask geotech to run L-pile for horizontal load).

In addition check pile shear.

If you have only downward load on pile you may stop reinforcement at about 15 feet below pile cap.

Good luck.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources