Define start AND end date
Define start AND end date
(OP)
Hi all,
I'd like to define a task that starts on the 02. Jan. 2004 and ends on 30. Jan. 2004.
Is it possible to say to project "Start date of the task should be 02. Jan 2004 and end date should be 30. Jan. 2004
AND PLEASE DON'T CHANGE THESE DATES."
Thanks in advance
I'd like to define a task that starts on the 02. Jan. 2004 and ends on 30. Jan. 2004.
Is it possible to say to project "Start date of the task should be 02. Jan 2004 and end date should be 30. Jan. 2004
AND PLEASE DON'T CHANGE THESE DATES."
Thanks in advance





RE: Define start AND end date
So long as work hrs or resources have not yet been defined, the default is using a start/end date to set the duration.
TTFN
RE: Define start AND end date
My example is that I want to plan the project management task of my project on a monthly base. That is, for each month of the current year I estimate an effort of 40 hours. Now I like to create a task "Project Mgmt" for each month that must not start before the first of the month and must not end after the last of the month.
It is this scenario that has lead me to the question of how to define two date restrictions for task.
Ruediger
RE: Define start AND end date
What Project does is to create a bunch of substasks which you can then edit for work hrs as well as the finish dates if needed.
TTFN
RE: Define start AND end date
Cheers.
MG