INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Define start AND end date
2

Define start AND end date

Define start AND end date

(OP)
Hi all,

I'd like to define a task that starts on the 02. Jan. 2004 and ends on 30. Jan. 2004.

Is it possible to say to project "Start date of the task should be 02. Jan 2004 and end date should be 30. Jan. 2004

AND PLEASE DON'T CHANGE THESE DATES."

Thanks in advance

RE: Define start AND end date

I'm  not clear on where you're having trouble.  

So long as work hrs or resources have not yet been defined, the default is using a start/end date to set the duration.

TTFN

RE: Define start AND end date

(OP)
Thanks for the question. Here's the background:

My example is that I want to plan the project management task of my project on a monthly base. That is, for each month of the current year I estimate an effort of 40 hours. Now I like to create a task "Project Mgmt" for each month that must not start before the first of the month and must not end after the last of the month.

It is this scenario that has lead me to the question of how to define two date restrictions for task.

Ruediger

RE: Define start AND end date

There's no clean way to do exactly what you're asking, BUT, you can insert a "Recurring Task" from the Insert menu, scheduled for the 1st day of each month with a duration of of something like 20 days, which will take of most months except possibly for Feb.  This insertion puts the start date for each month's task on the 1st working day of the month.

What Project does is to create a bunch of substasks which you can then edit for work hrs as well as the finish dates if needed.

TTFN

RE: Define start AND end date

If you are linking these dates to 2 separate tasks, you may want to set up a "Hammock". Follow the steps for this in the help menu.

Cheers.
MG

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources