Adjusting Gantt Chart
Adjusting Gantt Chart
(OP)
If you manage to reduce the time of the whole project by a couple of days, how do you actually show this change of time visibly on the gantt chart??
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
|
RE: Adjusting Gantt Chart
Make use of the Gantt Chart Wizard on the formatting menu, use one of the custom baseline modes. You'll need to set the baseline start/finish as well as actual start/actual finish. The format bar styles will show what the chart is actually presenting.
TTFN