×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

non existing cross sections method of measurment

non existing cross sections method of measurment

non existing cross sections method of measurment

(OP)
one engineer started to cross section a lake to be dredged, but never completed the work.  another engineer cross sectioned the lake post construction-excavation. The only measurment of the amounts removed are the truck load counts.  Any ideas on how to determine the volume of material removed by truck load if cross section data is not available?  

RE: non existing cross sections method of measurment

Get the average volume of each load.  Divide the total volume found that way be a factor of 1.15, fluff factor. this might give you aballpark number. the fluff factor is the increase in volume due to the excavation and dumping in the trucks. Look for pictures of the project.
Another way would be to use the weight of the material and do a compaction test on it. Bring it back to the same density as material very close to the 'lake'. I
f you have none of this data, use the volume of the water in the lake now as the removed quantity.

RE: non existing cross sections method of measurment

If the material is wet, as most dredging spills are, then there will not be any fluff.  You have to determine the amount of water in the material and calculate the material quantity based on the "average" load.

KRS Services
www.krs-services.com

RE: non existing cross sections method of measurment

The following formulae solve the above problem

 
  v1   = Dry density (loaded in truck )
  ---    ----------------------------------
  v2     Dry density ( in dreded area )

 v1 = volume of material excavated
 v2 = volume of material loaded

The following data required
 Dry density : This can be calulated by knowing the water content W (field )

Dry density = Bulk density / (1 + w )

Bulk density of loaded soil : weight/volume (loaded one truck soil)
water content : it will get by OVEN DRYING method

SECOND METHOD:

   V1/V2 = (1+ e1)/(1+ e2 )
e1= void ratio(in field)
e2= void ratio(loaded truck )
v1, v2 are same as above given notations
void ratio can be calculated by   e * Sr = W * G

where   e = void ratio , Sr = degree of saturation,        w = watercontent, G = specific gravity of soil
____________________________________________________________           A. RAVI SHANKAR B.Tech, INDIA , HYDERABAD

___________________________________________________________

RE: non existing cross sections method of measurment

As I understand it you have no initial ground sections but only cross-sections after excavation. Presumably,the contractor is claiming payment based on the quantity removed determined on the basis of the capacity of the trucks.  

Do you have any way to determine the original ground levels. How about taking some shots just outside of the excavated area. Does your post construction shots extend beyond the excavated area ( I presume that it does in nornal survey work of this kind). If so can you use the elevation of the unexcavated areas to establish original ground with some assumptions. This can be checked against the survey outside of lake area as suggested previously. I would use this info to determine the vol excavated.

This quantity would not likely agree with the load count volumes. In terms of truck loads with dredge spoil. It depends on the nature of the spoil material. If it is clay and comes up in excavated lumps after removal of an initial thickness then I would venture to say that the trucks would not be more than 80 % filled. I would use a factor of 1.10 appplied to the truck volumes in the same manner as dicksewerrat has indicated based on the assumption that inplace volume is being paid for.

Generally if no measurements were taken by survey and this was the basis for payment then one may have to strike a compromise with the contractor or one does not have much to hang on in a court of law. These are often long and drawn out issues that put the money in the hands of lawyers only.

Compromize is often the best route

RE: non existing cross sections method of measurment

It's not likely you will be able to agree with the contractor on the actual volume of soil removed.  Since the contractor was allowed to remove the material and simply count the truck loads, you may have to negetiate a rate per truck load and pay by the load.  This should have been agreed to prior to the work being done.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources