INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

WELDING FIXTURES

WELDING FIXTURES

WELDING FIXTURES

(OP)
Hi everyone. I am new here in this company and I one of my duties is making fixtures for fabrication. We mainly use hot rolled and high strength steel in all our parts that are used to make the final welded part.Our fixtures are mainly tack fixtures. However we have to compare our final welded parts to the engineering designed ones. After we weld the parts they are send to CMM in QC, that issues a rejection or accepted parts report. If accepted the fixture is welded and send to production. If rejected we have to try to make some adjustement to the fixture and redo the whole process again.I have a problem with the existing process and QC does not agree with me.
I want the tacked parts to be accepted so we can have a reference for adjustments. What do you guys think? Any other suggestion is welcome. Anyone out there make fixture under different procedue?

Thank you guys.

MT
Manufacturing eng.

RE: WELDING FIXTURES

The final welded parts will provide more info than a tack welded part. The welded part will have experienced some degree of dimensional shrinkage as the welds have cooled. This will be apparent if you measured a welded and tack-welded part in the CMM.

If there are substantial dimensional variations from 2 parts welded in the same fixture, then I would approach the reviewing welding sequence and welding parameters - provided the fixture has a history of producing accepatble weldments. If 2 (or more) welders are are joining sub-assemblies in the same manner using the same heat input, the parts should be identical.

Having worked in an aerospace environment myself, most weldments are fabricated in fixtures which have been inspected and re-inspected about every 6-12 months depending on the part. Many fixtures also had a set-up procedure and welding sequence documentation. This is to ensure repeatability.

Only a few large fixtures required disassembly and pretensioning of the parts to be welded to counter weld shrinkage. Even these (through inspection & trial & error) had the adjusment required factored in to maintain the repeatability. The parts came out the same regardless of who performed the welding. We often worked to tolerances of 0.030" or less. These included very small parts (<6" in length) and parts that were relativley large (wing spars for a military transport plane).

RE: WELDING FIXTURES

(OP)
Hi again. I just want to add that we inspect the welded parts and then make correction to the fixtures.Any distortion to the parts used is hard to predict.I was thinking that the tacked parts,ounce inspected by QC, will give us some information to the deviation due to distortion.Our tolerances are +/-0.030".


We usually recheck our fixtures for every x-parts welded.

Thank you again.

MT

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources