INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Post Weld Heat Treatment

Post Weld Heat Treatment

Post Weld Heat Treatment

(OP)
Hi Everyone,

If vessel clips are welded to the reactor that requires PWHT.  Do we have to PWHT the entire reactor or just localized area?.  What section of ASME section VIII Div. 1 specify the requirements for this particular case.

Thank you very much in advance for your help.

azn4850

RE: Post Weld Heat Treatment

Don't know the code section, but you shold be able to do a local PWHT-unless the vessel is 304 SS, etc.  You might also be able to do a "temper bead" weld.

RE: Post Weld Heat Treatment

ASME SecVIII Div1 UW-40

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources