Roadway User Delay Costs
Roadway User Delay Costs
(OP)
Does Anyone out there have an idea on the Life Cycle Cost Roadway User DELAY costs analysis for pavement design. I have no idea what the format is going to look like without a detailed raodway traffic analysis!!!
I have the FHWA LCCA handbook and it mentions a Roadway User Delay Cost but then the term just withers away as the book goes on....
Can Anyone point me in a direction to defining what exactly is the Roadway User Delay Cost and how to go about simply calculating it......
I have the FHWA LCCA handbook and it mentions a Roadway User Delay Cost but then the term just withers away as the book goes on....
Can Anyone point me in a direction to defining what exactly is the Roadway User Delay Cost and how to go about simply calculating it......





RE: Roadway User Delay Costs
RE: Roadway User Delay Costs
The costs however prove to be good fodder for politicians and opponents to a specific project where cancellation or stalling is their agenda.
KRS Services
www.krs-services.com
RE: Roadway User Delay Costs
But you people are correct on saying that the number does not really play a roll within a design calc...
My guess is that it is mainly political
RE: Roadway User Delay Costs
If you are comparing to construction methods or materials, one of which will require no maintenance for 10 years and the other will require maintenance in 5 years. The first method/material costs more initially, however, if the second method/material creates twice the delay cost (at 5 years and 10 years) then its cost may be more in the long term. The question should become "What is in the best long interests of the public?". However, this generally becomes either a political decision or a decision made based on the amount of money available for the project.
Also, as has been stated, figuring the real value of the delay costs is very difficult at best.
RE: Roadway User Delay Costs
You are absolutely correct and I find it refreshing to learn that I am not the only lone waddie in this regard. I have been in the business now for over 17 years, and it still amazes me as to how many designs do not accurately consider the maintenance/upgrade costs as a fuction of the lifecycle of the infrastructure. Using either present value or future value formulas, it is a critical component to any project I undertake because in some instances, politicians and decision makers may elect to spend more (as today's dollar) than a future dollar which has compounded due to inflation and other increases. In your case you translate that cost as a deferred or scheduled maintenance upgrade.
I provide this analysis as a standard component of my designs and recommendations regardless of whether I am dealing with water, sewer or transporation issues. Given my municipal background (dealing with Council's), my habit was bourne out of necessity to anticipalte the questions or stave off issues, nonetheless it has proven valuable for some of my consultant client's as well and enabled them to secure a unique credibility with municipalities.
KRS Services
www.krs-services.com
RE: Roadway User Delay Costs
But getting back to the question at hand...
This user cost delay gets extremely complicated in situations like a clover leaf interchange where there is signal timing on off ramps and vertical cleanrance issues...