What is the American code for lifting sling design ?
What is the American code for lifting sling design ?
(OP)
Hi, I am a British Engineer.
I was wondering if any of you could tell me what the American code is for the design, and manufacture of a 4 leg lifting sling ?
i.e. the ropes e.t.c. that a crane requires to lift a heavy object.
I was wondering if any of you could tell me what the American code is for the design, and manufacture of a 4 leg lifting sling ?
i.e. the ropes e.t.c. that a crane requires to lift a heavy object.






RE: What is the American code for lifting sling design ?
RE: What is the American code for lifting sling design ?
ASME B30.20a-2001 Structual and Mechanical Lifting devices. Section 20-1.2.2 Construction
CMAA crane requirements
AASHO 1.6.17
Steel Construction Manual-AISC
Occupational Safety and Health Administration (OSHA) 29 CFR standard 1926.753(e)(2) and 1926.251
American Society of Testing and Materials Specifications A391
Naval Facility Command NAVFAC-307
American National Standards Institute, "Below The Hook Lifting Devices"
RE: What is the American code for lifting sling design ?
In Britain we have BS1290, 'Wire rope slings and sling legs for general lifting purposes'.
I work in the offshore industry in Britain, and have not got access to American codes.
I am writing a spreadsheet that designs 4 leg slings to all the common codes i.e. DNV Marine Operations, DNV Offshore Containers, BS1290 e.t.c., and would also like to include the standard American design procedure. There must be one commonly recognised standard in the USA, that gives guidance on the design, proof testing, identification stamping, and certification, of a 4 leg sling ?
If so could someone give me the name of this specific code, and the reference sections ?
RE: What is the American code for lifting sling design ?
RE: What is the American code for lifting sling design ?
http://www.csa-intl.org/onlinestore/GetCatalogDrillDown.asp?Parent=2860