To calculate the minimum size of attachment welds for nozzles and flange to nozzle neck welds (UW-16 and UW-21, respectively), is "tn" defined as the nominal thickness of nozzle wall minus corrosion allowance minus 12.5%tn of mill tolerance (when pipe is used)?
Thank you!
To calculate the minimum size of attachment welds for nozzles and flange to nozzle neck welds (UW-16 and UW-21, respectively), is "tn" defined as the nominal thickness of nozzle wall minus corrosion allowance minus 12.5%tn of mill tolerance (when pipe is used)?
Thank you!





RE: Minimum Requirements for attachment welds at openings
RE: Minimum Requirements for attachment welds at openings
prex
http://www.xcalcs.com
Online tools for structural design