INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Spec Break

Spec Break

Spec Break

(OP)
All,
In designing a piping system with variable pressure rating, what is the consideration when specifying the piping spec break? Must there be a valve at every spec break? Is there any code on this?

Thanks

RE: Spec Break

You can declare a spec break anywhere you like, but how would you maintain the change without a control or hand valve?  You could protect the system at different pressures with either mutiple or a resetable relief valves as an option, or just have the various pressure producing points have a relief valve for the variable pressures.

RE: Spec Break

Try API RP 14E, it gives a very good guide in piping system design for offshore industries but is very applicable for onshore as well.

Best of luck.

RE: Spec Break

Spec break is required to be defined when,

1. Operating parameters are changed like pressure and temperature. Let down pressure control valve is an example where rating of the downstream flange is determined by the specified pressure in the line after the let down. Important to note that the low pressure side must be protected by a safety relief device to avoid over pressure due to control valve malfunction or physical blockage,

2. Changing the chemical characteristics / composition of the fluid handled. For example, piping material change is essential and must be shown as a spec break on the P&ID at and downstream of a mixing tee where 98% sulfuric acid is diluted with water, for regeneration of demineralizers.

Bottom line is, there is always a fitting (valve, tee or an injection quill) downstream of which, illustration of the spec break is to be shown.

Ali Ansari

RE: Spec Break

one of the situation where i could envisage a spec break with out a valve could be after a gas blowdown valve, where imediately following the valve a cold spec pipe could be used, and after a certain distance of pipe you could switch to a normal pipe.

Best Regards

Morten

RE: Spec Break

(OP)
Thank you all for being all the comments. Its has been very helpful.

 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources