Help: Changing Task/Subtask Dates Automatically
Help: Changing Task/Subtask Dates Automatically
(OP)
I have many tasks set in PRoject 2000, each with 5-8 subtasks.
Is there any way to simply DRAG AND DROP the main TASK to a different start date, so that the subtask dates move automatically...keeping their respective timefram assignments?
So far, I can only do this by manually changing or draging and dropping the dates for each individual subtask.
Thanks
Is there any way to simply DRAG AND DROP the main TASK to a different start date, so that the subtask dates move automatically...keeping their respective timefram assignments?
So far, I can only do this by manually changing or draging and dropping the dates for each individual subtask.
Thanks





RE: Help: Changing Task/Subtask Dates Automatically
If each subtask is linked to its predessor, moving the first task of a group will force all the other tasks to follow.
TTFN